Smart Manufacturing Results

What Changed After Smart Manufacturing? OEE, Yield, Scheduling, and Reporting Records

Once the system is running, the discussion has to return to production KPIs. This chapter summarizes changes observed during Power Tech Mold's smart manufacturing and production-improvement period, including OEE, yield, energy use, scheduling time, production reporting, and warehouse operations. These figures reflect the combined result of multiple improvements rather than the effect of a single software function.

The previous chapters covered machine connectivity, MES, production reporting, Cycle Time deviation alerts, GA production scheduling, and mobile warehouse operations. Once these functions are used on the floor, the important question is not how many new technologies were installed. The question is whether recurring production work became easier to manage.

This chapter therefore focuses on measurable operating indicators rather than a separate “AI result.”

The following figures are internal records from the system-implementation and production-improvement period at Power Tech Mold. OEE, yield, and energy use are also affected by equipment, molds, materials, process settings, scheduling, production management, and product mix. They should not be interpreted as guaranteed results from installing MES, machine connectivity, or AI.

Author: Jush Li

60% → 75–85%OEE during the improvement period
92% → 97%Product yield
Down 8–12%Overall electricity use during the improvement period
3–4 hr → 20–30 minScheduling work time
2 min → 15–30 secSingle production-reporting operation
90 sec → about 10 secSelected warehouse receiving operations

5.1 OEE Improvement

After machine-status monitoring was introduced, downtime and Cycle Time deviations became easier to see without waiting for the daily report to be completed.

OEE: approximately 60% → 75–85%

During the overall improvement period, OEE increased from approximately 60% to a range of about 75–85%. Actual values still vary with product mix, mold-change frequency, order volume, and equipment condition.

Cycle Time deviation alerts identify machines that differ from their historical baseline. If a product normally runs at about 30 seconds on a specific machine and current cycles remain near 35 seconds, the system highlights the difference.

The production team still investigates the reason. Cooling changes, robot waiting, mold condition, material, process adjustment, or other factors may be involved.

Compared with the internal pre-improvement baseline period, unplanned downtime was reduced by approximately 15 hours per month after changes in scheduling, downtime-reason management, and shop-floor response.

Machine utilization records during the same improvement period increased from about 68% to near 90%. Utilization and OEE are tracked separately because OEE also includes performance and quality factors.

Machine connectivity does not automatically increase OEE. Its practical contribution is that the factory can see when the machine stopped, how long it stopped, and when the loss began, making the actual cause easier to investigate.

5.2 Product Yield Improvement

Quality improvement was not produced by a single alert. The more important change was the ability to return from a defect record to the corresponding production history.

Once production reporting links the work order, time interval, and machine data, QC can check which machine and mold were used and review Cycle Time and other stored process data from the same period.

Yield: approximately 92% → 97%

During the broader process and quality-improvement period, internal yield records increased from approximately 92% to approximately 97%.

The practical difference is that the abnormal period can be identified. Instead of relying only on operator memory, the team can first trace the work order and production time.

Compared with the internal pre-improvement baseline period, rework- and scrap-related cost decreased by approximately 40% after defect classification, process adjustment, mold improvement, and shop-floor quality management were combined.

Cycle Time deviation and product defects do not necessarily have a direct causal relationship. Cycle Time is useful as a process-change signal; final quality still depends on dimensional, visual, functional, and product-specific requirements.

5.3 Energy Use Improvement

Energy performance cannot be evaluated only from the monthly electricity bill. Without production context, it is difficult to separate the effect of output volume, idle time, machine efficiency, or product cycle time.

The practical approach is to compare machine operation, production time, and actual energy records on the same timeline.

Overall electricity use during the improvement period: down approximately 8–12%

With changes to machine scheduling, idle management, process improvement, and energy review, overall factory electricity use during the improvement period decreased by approximately 8–12%.

When machine electricity use is viewed together with production time, the factory can investigate whether higher consumption is caused by excessive idle time, different product cycle times, or unnecessary waiting created by the schedule.

Some individual months showed electricity-cost improvement of approximately 10–12%, but electricity cost is also influenced by production volume, working days, product mix, season, and tariff structure. It should not be presented as a fixed “system energy-saving rate.”

The next step in energy management is to move from total plant electricity toward unit-energy analysis by machine, work order, and product — for example energy per cycle, per kilogram of finished product, or the same product produced on different machines.

5.4 Scheduling Time Reduction

Scheduling was one of the easiest processes to compare before and after digitalization.

Previously, planners manually checked machines, molds, due dates, and existing orders. When an urgent order arrived, the existing schedule often had to be reviewed again.

Typical scheduling work: approximately 3–4 hours → 20–30 minutes

GA first processes the defined constraints and produces an initial schedule. The planner then adjusts it according to actual production conditions instead of starting from a blank schedule.

The algorithm can handle due dates, job sequence, available machines, molds, and other quantified constraints. Mold repair, unexpected machine downtime, staffing, and special customer requests still require planner judgment.

Internal operation records show that some urgent-order insertions could reach an initial reschedule plus manual adjustment in approximately eight minutes.

The important point is not that “eight minutes guarantees the due date.” It is that a large amount of repetitive comparison can be completed quickly enough to give the planner a usable starting point.

GA does not replace the production planner. It performs repetitive calculations first. The planner still provides the shop-floor information the model does not know.

5.5 Production Reporting and Warehouse Time Reduction

Production reporting and warehouse improvements were more straightforward: remove repeated data entry.

If the work order, item number, and machine already exist in the system, operators should not type them again. If a QR Code identifies a warehouse record, the system can reuse existing data.

Single production-reporting operation: about 2 minutes → 15–30 seconds

After simplifying the RWD reporting interface, the time required for one shop-floor reporting operation decreased by more than 75%.

The purpose of reporting is not to make the operator enter more data. Operators only need to provide information the machine cannot know, such as manually judged defect quantities, abnormal causes, or necessary notes.

Selected warehouse receiving operations: about 90 seconds → about 10 seconds

With QR Code identification and the responsive warehouse interface, existing item, document, and work-order data can be reused instead of being entered again in ERP.

Internal operation records showed approximately 70% improvement in processing efficiency for these tasks, while also reducing opportunities for manual item-number, quantity, or document-entry errors.

One of the most direct benefits of shop-floor digitalization is sometimes not a complex AI model. It is simply that the same data does not have to be entered once in ERP, written again on paper, and typed a third time in production reporting.

Across Sections 5.1 to 5.5, the changes are not the result of one software module. Machine connectivity makes states more visible, MES connects work orders with production history, scheduling reduces repetitive calculation, and RWD / QR Code functions reduce repeated data entry.

For Power Tech Mold, these KPIs are primarily useful as a baseline. When the factory changes scheduling, equipment, molds, or work methods later, the team can compare the result instead of relying on memory.